| Activity | Description | Category | Unit | Price | Status | Added | |
|---|---|---|---|---|---|---|---|
| 05 Concrete Work | White Cement | Material | Bag | Not priced yet | Draft | 13 Jul 2026 | |
| 05 Concrete Work | 1/2" Metal (chip) | Material | Cube | LKR 16,500.00 | Draft | 12 Jul 2026 | |
| 04 Random Rubble Masonry Work | 4" - 6" Rubble | Material | Cube | Not priced yet | Draft | 11 Jul 2026 | |
| 01 Site Preparation & Excavation | Backhoe loader hire | Plant | Day | LKR 18,500.00 | Draft | 10 Jul 2026 | |
| 11 Doors and Windows | Teak door frame 3"x4" | Material | No | Not priced yet | Draft | 09 Jul 2026 | |
| 05 Concrete Work | Cement | Material | Bag | LKR 2,400.00 | Promoted | 28 Jun 2026 | M-026 |
| 04 Random Rubble Masonry Work | Sand | Material | Cube | LKR 18,000.00 | Promoted | 28 Jun 2026 | M-113 |
| 05 Concrete Work | Mason | Labour | Day | LKR 3,500.00 | Promoted | 25 Jun 2026 | L-009 |